Good afternoon,
On Saturday, June 27th, Jacobson Hall, CAB, and Clark Tower will have the normal Power shutdown. There will be emergency power, but no one should be in the buildings.
Also, on this date the contractor will be making changes to the 480V loads in WHA. This will affect normal lighting, air handling equipment and Lab air and vacuum. If the researchers need lab air and vacuum, they should make other arrangements. Since the normal lighting will be off no one should be in the building. This shutdown will start at 6 AM and last about 8 hours.
On Saturday, July 11th , the NAB and Silverman will have the normal power shutdown while the contractor makes changes to the 480V loads in WHA. These loads come from the distribution equipment DV that takes care of the exhaust fan towers and the penthouse. This shutdown will start at 6 AM and last about 8 hours. Since exhaust fans (Hoods) will be down, any items stored in the hoods should be secured elsewhere.
No Emergency Power will be affected
If you have any questions or concerns, please feel free to contact me at 315-243-5974 or respond to the e-mail.
John Ders
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/jh-cab-ct-utility/attachments/20260618/74496a65/attachment.html>
More information about the Jh-cab-ct-utility
mailing list