[util] [EXTERNAL] UH South Wing Radiant Heating Shutdown Notice / Friday, January 8th / 6:00 AM - 4:00 PM

Mary E. Lent LentM at upstate.edu
Thu Jan 7 13:31:26 EST 2021


We need to complete a radiant heat shutdown on Friday January 8th starting at 06:00 hours related to work being completed for the Heart and Vascular Project. The shutdown work is expected to be completed prior to 16:00 hours. This shutdown will only affect the radiant heating system in the UH south wing. No other areas will be affected. Supplemental heating will be provided utilizing the fan system to assist with the additional heating needs in the affected areas.



Please contact project manager Scott Bloss at 315 863 5576 if additional information is required.