[util] Electrical Shutdown Notice / Friday, July 16th / 6:00 AM - 10:00 AM

Mary E. Lent LentM at upstate.edu
Thu Jul 15 14:00:09 EDT 2021


In support of Phase 2 Heart & Vascular Project we will be performing an electrical shutdown of certain circuits within the Heart Vascular Center on Friday July 16th from 0600 - 1000 hrs. to relocate conduits.

Areas to be affected will be Recovery rooms 11 & 12, clean storage room, EP Laboratory Pyxis machine circuit and EP Control room 1 circuit.

EP Control room & Laboratory circuits will be done 1st and re-energized for surgery scheduled to start around 0800 remaining work in area will be completed after these circuits are back on line.

Any questions should be directed to Richard Peterson concerning this outage.

Richard Peterson
Associate Facilities Project Manager
petersri at upstate.edu<mailto:petersri at upstate.edu>
(860) 885-4345

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/uh-utility/attachments/20210715/06c582a9/attachment.html>


More information about the Uh-utility mailing list