[util] Electrical Shutdown Notice / Friday, July 23rd / Starting at 1:00 PM

Mary E. Lent LentM at upstate.edu
Fri Jul 23 11:14:41 EDT 2021


Phase 2 for Heart & Vascular Project requires the relocation of existing conduit feed lines that supply power to existing Isolation Panels within the Cath Lab. Which will require an electrical shutdown.

The shutdown will start at 1300 hrs. on Friday 7/23/21. The length of the shutdown is anticipated to be approximately 8 hours. The area impacted will be contained to the Cardiac Cath Lab.

We will have an additional electrical shutdown in the EP Lab once Cath Lab work is complete and EVS has cleaned the room for patient occupancy.

This will take place on Friday 7/23/21 in the evening after the Cath Lab reopening. The length of time for this interruption will be approximately 3-4 hours.

The only area to be affected by the second interruption will be the EP Lab.

Any questions concerning the shutdown should be directed to Richard Peterson at number below.

Richard Peterson
Associate Facilities Project Manager
petersri at upstate.edu<mailto:petersri at upstate.edu>
(860) 885-4345

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/uh-utility/attachments/20210723/9dd60e3f/attachment.html>


More information about the Uh-utility mailing list