[util] Sprinkler Shutdown Notice / Saturday, July 31st / 5:00 AM

Mary E. Lent LentM at upstate.edu
Thu Jul 29 15:02:53 EDT 2021


In support of Heart & Vascular Project we will be performing a sprinkler shutdown for 6 West active Heart & Vascular active area. We will be tying in the North side of 6 West to the new South side sprinkler piping.

The affected area will be the existing Heart & Vascular surgical (IR, Cath & EP rooms),  recovery rooms (6500, 6501, 6502, 6503, 6510, 6511 & 6512), nurse station (6507) & rest rooms (6506 & 6508).

Start time for shutdown will be 0500 and will approximately 8 hours in duration.

Any questions should be directed to Richard Peterson below. TY

Richard Peterson
Associate Facilities Project Manager
petersri at upstate.edu<mailto:petersri at upstate.edu>
(860) 885-4345