[util] Project Number 1426 - 7E Control Air Compressor.

Thomas Slater SlaterT at upstate.edu
Tue Aug 9 11:26:39 EDT 2022


Project No.:  1426
Project Name:  7E Control Air Compressor

CONSTRUCTION NOTICE:

A planned electrical outage affecting the East Wing and East Tower will take place on Thursday, August 11 from 10:00 AM to 12:00 PM.  The outage has been planned to maintain uninterrupted power to all emergency and normal power electrical outlets in the East Wing and East Tower.  In addition, power to all infrastructure systems and equipment will remain uninterrupted with the exception of power to exhaust fans serving AIIR's on 6H, 6I and 6K requiring the rooms to be used as regular patient rooms or closed as determined by Infection Prevention and the Units affected.

Please note should you experience a loss of power anywhere in the East Wing or East Tower during the planned outage period contact Aaron Petty at 315-464-4230.

For questions or concerns regarding the planned outage please contact Nick Steffen at 315-530-8014 or steffenn at upstate.edu<mailto:steffenn at upstate.edu>."


Thank you.

Nick Steffen, RA
Architect/Project Manager

Design and Construction
SUNY Upstate Medical University

Phone: 315-464-3815
Mobile: 315-530-8914
Email:  steffenn at upstate.edu<mailto:steffenn at upstate.edu>

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/uh-utility/attachments/20220809/fd81b785/attachment.html>


More information about the Uh-utility mailing list