[util] UH South Wing Brick Repair & Window Replacement Project / Impacted Areas / Starting Monday, February 7th

Mary E. Lent LentM at upstate.edu
Fri Feb 4 09:13:11 EST 2022


UH South Wing Brick Repair & Window Replacement Project:

The window replacement portion of the South Wing Brick Repair and Window Replacement project will be starting on February 2, 2022. The portion of the work scheduled to be completed this week February 2-4 will not impact staff or patient areas.

The following is a list of the rooms and areas that will be impacted by the window replacement project.


Window Replacement Installation UH South Wing

Day/Date         Affected rooms east facade             Affected rooms west facade

1-2 - 2/2/22           Corridor 5700
2-3 - 2/3/22            Corridor 4700
2-4 -2/4/22             Ramp 4760 / 7705X

Impacted Staff Areas
4 - 2/7/22               6717, 6722A, 6723A                                 6816, 6818A, 6812
5 - 2/8/22                6723,6724, 6725                                        6820A, 6818, 6816
6 - 2/9/22               5720B, 5722, 5724, 5727,5729              5800, 5801, 5802, 5803
7 - 2/10/22             6726, 6727, stair tower                          5804, 5805, 5806, 5808
8 - 2/11/22              5734, 5736, stair tower                            5809, 5811, 5813
9 -2/14/22                                                                                          5814, 5819, 5820, 5821, 5823, 5824
10 - 2/15/22                                                                                      4809, 48104704, 4709, 4710, 4711, 4717
                                                                                                                4718, 4719, 4720
11 - 2/16/22                                                                                      4852A, 4852B, 4848, 4847, 4811, 4810
                                                                                                                3800B, 3802,
12 - 2/17/22                                                                                      3802, 3804, 3805, 3806, 3813, 3814, 3815,
                                                                                                                3816, 3818
13 - 2/18/22                                                                                      3807, 3808, 3829A, 3809B, 3809C,3810, 3811
                                                                                                                2800, 2800, 2800
14 - 2/21/22                                                                                      2800, 2800, 2800, 2800, 2800
15 - 2/22/22                                                                                       1804A, 1804B, 1805, 1806, 1806C,1806B 1810A

The intent is to remove the existing window and install the replacement window on the same day. We will be visiting the impacted occupied areas in next couple of days to discuss the work in greater detail with staff.

Please contact Scott Bloss, RA,  Assistant Director of Design & Construction at 315-863-5576 with any questions.


Scott Bloss RA
Assistant Director

Upstate Design & Construction
650 South Salina Street
Syracuse, New York 13210
Ph. 315 464 9915
Cell 315 863 5576

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/uh-utility/attachments/20220204/4deab167/attachment.html>


More information about the Uh-utility mailing list