[util] Hyperbaric Expansion #1058

Thomas Slater SlaterT at upstate.edu
Wed Oct 5 09:24:46 EDT 2022


In consideration of the Hyperbaric Expansion Project ( # 1058) there will be a Medical Gases shutdown on Thursday (10/6/22) starting around 1730 hrs.

Areas affected will be Clinical Engineering room 403B, Radiation Safety Lab rooms 640, 642, Hyperbaric rooms 1415, 1416, 1419, 1420, 1423, 1425, 1501 & 1510.

Scheduled start time: Thursday 10/6/22 1730 hrs. / Duration of shutdown: 4-hrs.

Any questions can be directed to Richard Peterson (860) 885-4345

Richard Peterson
Associate Facilities Project Manager