[util] Electrical Shutdown
Kimberly J. Austin
AustinK at upstate.edu
Fri Jan 27 08:40:41 EST 2023
In consideration of the Hyperbaric Expansion Project (1058) we will be performing an electric shutdown affecting panels ELW1 & ELW1A on Saturday 1/28/23.
Area affected will be AP-1 & Room 7 in ODS which has been coordinated.
Time of shutdown will be Saturday (1/28/23) at 0600, length of electric interruption will be approximately 2 - 4 hr. duration
Any questions should be directed to Richard Peterson (860) 885-4345
Richard Peterson
Associate Facilities Project Manager
petersri at upstate.edu<mailto:petersri at upstate.edu>
(860) 885-4345
Kimberly Austin
Administrative Assistant
Physical Plant MOC Center
Room 1806 UH
PH:315-464-4230
FAX: 35-464-4711