[util] Electric Power Interruptions UH, East Wing, East Tower, CWB, Weiskotten Hall, and Setnor. Tentatively scheduled for 5:00 am – 6:am am Monday May 12th, 2025

Brittany Sprague SpragBri at upstate.edu
Wed May 7 15:24:05 EDT 2025


ELECTRICAL POWER NOTICE FOR

Downtown Campus Buildings



TO:                 All Departments with Space in UH, East Wing, East Tower, CWB, Weiskotten Hall, and Setnor


SUBJECT:      Electric Power Interruptions UH, East Wing, East Tower, CWB, Weiskotten Hall, and Setnor. Tentatively scheduled for 5:00 am – 6:am am Monday May 12th, 2025

TODAY’S DATE:                   May 7th, 2025

WORK PERFORMED ON:   May 12th 2025


In order to return our electric system to normal after National Grid repairs, we will be conducting switching to building feeds listed below tentatively between the hours of 5 am and 6 (dependent upon National Grid successful repairs which may not be completed until late Friday,9May2025). This will cause power losses from 1 to 10 seconds while we do switching. Emergency power circuits will see a loss similar to generator testing.



***East Wing- Please use OR’s 3,5,and 8 prior to switching and until an all clear is given in the morning.

MRI #2 and Emergency Department CT #1 will also be impacted and should be shut down during switching.

Before any switching is done, we will walk the 5E OR’s, 3N OR’s and 6 West & South Heart & Vascular.

Telemetry monitors may also see a blip and a 1-2 min reboot, but no data will be lost.

This is what you can expect to happen starting at 5:00 a.m.

UH, CWB, East Wing and East Tower; Will experience a loss of some of your normal power circuits for 1 to10 seconds while we conduct switching. Emergency power circuits will see a loss similar to monthly generator testing.

Weiskotten Hall, and Setnor: Some of the normal power circuits will lose power for 1-10 seconds while we conduct switching in the morning. Emergency power will see a loss similar to monthly generator testing. You will see the same impacts in the afternoon when we switch back to normal operations.

Other buildings (Cancer Center, Setnor, Gama Knife, Silverman etc.) are not affected.

If you have any questions, please contact Larry Blanchard at 315-464-7371

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/uh-utility/attachments/20250507/4a00ef5c/attachment.html>


More information about the Uh-utility mailing list