[util] Planned Electrical Shutdown – Weiskotten Hall Addition (June 9, 2026)

Jason Tarantino TarantiJ at upstate.edu
Mon Jun 1 14:20:06 EDT 2026


Hey Team,
To support ongoing work for the WHA power upgrade project, a planned electrical shutdown will be required.
Please see details below:

  *   Date: June 9, 2026
  *   Time: 6:30 AM – 3:00 PM (anticipated completion)
  *   Location: Weiskotten Hall Addition (WHA)
  *   Affected Area: North half of WHA (from elevator lobbies to the University Hospital end)
  *   Floors Affected: Basement through 9th Floor (all floors)
  *   Impact:
All floors in the affected area will be without normal power during the shutdown period.
Emergency power and emergency lighting will remain available.
  *   Additional Information:
Personnel are requested to be on site to monitor rooms and equipment during the outage.
A longer duration is possible but is not anticipated.

If you have any questions or concerns, please contact:
John Ders
315-243-5974

Best regards,

Jason Tarantino
Administrative Assistant Trainee 2
Physical Plant – Maintenance Operations Center
Upstate Medical University
Room 1806
📞 315-464-4230

Tough times don’t last, but tough people do.
— Robert H. Schuller

[image]
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/wh-set-utility/attachments/20260601/15d17acf/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image.png
Type: image/png
Size: 6554 bytes
Desc: image.png
URL: <http://lists.upstate.edu/pipermail/wh-set-utility/attachments/20260601/15d17acf/attachment.png>


More information about the Wh-set-utility mailing list