[util] WHA shutdowns & cleanings

Anne Hodges HodgesA at upstate.edu
Fri Mar 27 07:20:12 EDT 2026


Starting on March 31st the following is a list of electric panel cleanings the contractor needs to accomplish.

Start time will be 6AM.


These panels all need to be cleaned because of potential for hazardous material.

No emergency power will be affected.

The lab panels are fed from the chase panels.  The lab panels will be cleaned first and then reenergized only to be shut down again while the chase panels are being cleaned, all will be reenergized in about 10 minutes.

Some lab panels must have containment built in the hall and will require the containment stay in place until clean air sample results are received.



March 31st S7A, S7B, S7C, S7D.   These rooms will be affected: 7303 & 7299.  These rooms may be down for (2) days if clean air’s don’t come back.

April 1st, S8D, S8A, S8B, S8C, P8MA.  These rooms will be affected 8303 & 8299. These rooms may be down for (2) days if clean air’s don’t come back.



April 2nd P5N, P5S, P7S, S7E, S7F, S8D

April 3rd P4M, P4N, S4A, S4B, S4C, S4D, S4E, S4F

April 6th   P3N, P4S, S3A, S3B, S3C, S4D, S4G, S4H, S4I

April 7th P3S, S3D, S3E, S3E, S3F, S3G, S3H, S3I

April 8th P2M, P2N, S2A, S2B, S2C, S2D, S2E, S2F

April 9th P2S, S1G, S1H, S1I, S2G, S2H, S2I



We have communicated the interruptions with all occupants affected  to minimize disruptions as much as possible.

If you have any questions or concerns, please feel free to contact John Ders at 315-243-5974.

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/wha-utility/attachments/20260327/33a1c0e8/attachment.html>


More information about the Wha-utility mailing list