[util] Power shutdown WHA 9th floor
Yvette Stewart
StewartY at upstate.edu
Wed May 20 07:22:27 EDT 2026
Our original date for this shutdown was May 15th and has been rescheduled to accommodate testing in the area.
The new date is Friday May 22nd
On Friday, May 22nd, power to the 9th floor of WHA will be shut down to allow the contractor to continue work required for the WHA power upgrade.
Panel H9M feeds kitchen equipment and on Fridays the kitchen is shutdown allowing us the time to do this work.
Panel L8 is a lighting panel on 8 of WHA and the 8th floor will be without general lighting. There will be emergency lighting.
Power off is estimated at 2 hours.
The start time would be 6:30 AM for drilling into the panels with power outage to occur following.
The drilling will occur early in the morning to reduce the noise throughout the building.
If there are any questions or concerns, please feel free to contact me at 315-243-5974.
John Ders
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/wha-utility/attachments/20260520/5b8bc03f/attachment.html>
More information about the Wha-utility
mailing list