[util] WHA Power Outage
Yvette Stewart
StewartY at upstate.edu
Tue May 26 11:28:45 EDT 2026
Notice of Electrical Shutdown
Weiskotten Hall Addition
On Tuesday, June 9, 2026 power to the north half of WHA (from the elevator lobbies to the University Hospital end of the building) on ALL floors (Basement to 9th) will be shut down to allow the contractor to continue work required for the WHA power upgrade.
All floors will be without regular power. There will be emergency power and lighting.
The shutdown will begin at 6:30 AM and is expected to be completed by 3:00 PM. Longer duration is possible but not anticipated.
Please have personnel on site to monitor the rooms and equipment. If there are questions or concerns, contact John Ders at 315-243-5974.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/wha-utility/attachments/20260526/f5a31393/attachment.html>
More information about the Wha-utility
mailing list