Shutdown Notice:

In support of the Heart & Vascular Project we will be shutting down ventilation air units 8.1 & 6.2 that supply ventilation air to the 6th floor west wing in order to complete ductwork modifications.

The 6W Heart & Vascular EP Lab 6515, Control Room 6516 & Clean Storage 6514 will be impacted along with the recovery areas. The IR Lab and Cath Lab spaces will remain operational.

Other areas impacted include the following areas.

Bathroom 6342
H&V recovery bays area
H&V Staff Lounge
6th Floor Main Elevator Lobby
H&V Men & Women locker rooms

The shutdown will occur on Saturday, April 24th starting at 6:00 AM (0600  hours) with an expected duration of 8 hours.

The shutdown has been coordinated with the Heart & Vascular Staff.

If you have any questions or concerns please contact Scott Bloss at 315-863-5576


Scott Bloss
Architect / Project Manager

Upstate Design & Construction
650 South Salina Street
Syracuse, New York 13210
Ph. 315 464 9915
Cell 315 863 5576

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/uh-utility/attachments/20210423/41604e3b/attachment.html>


More information about the Uh-utility mailing list