In support of Phase 2 Heart & Vascular Project we will be shutting down EF-22, which is general exhaust on 5th floor South, North end of floor. This will have no affect on any laboratory hood exhaust.

We will be shutting down EF-22 this Saturday July 10th at 0600 hrs. The shutdown duration will be approximately 8 - 10 hrs.

Electric to fan is scheduled to be disconnected immediately after 0600 shutdown and will be re-hooked to new EF-22 after all duct connections are in place  the same day.

Any questions concerning this shutdown should be directed to Richard Peterson (860) at contacts below, TY.

Richard Peterson
Associate Facilities Project Manager
petersri at upstate.edu<mailto:petersri at upstate.edu>
(860) 885-4345


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/uh-utility/attachments/20210708/4b0082ee/attachment.html>


More information about the Uh-utility mailing list