In consideration of Heart & Vascular Project (#1232) we will be doing a shutdown to run Laser outlets in EP Lab, IR Lab & ENDO Lab on consecutive nights.


Monday night 3/28- Electrical work in room 6514- EP Lab start after 19:30 hrs. duration 8 hrs.



Tuesday night 3/29- Electrical work in room 6604- ENDO Lab start after 19:30 hrs. duration 8 hrs.



Wednesday night 3/30- Electrical work in room 6610- IR Lab start after 19:30 hrs. duration 8 hrs.



Areas affected will to confined to the OR being work on that night.



Coordination with Heart & Vascular staff has been worked out.



Any questions should be directed to Richard Peterson at contacts below.


Richard Peterson
Associate Facilities Project Manager
petersri at upstate.edu<mailto:petersri at upstate.edu>
(860) 885-4345
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/uh-utility/attachments/20220325/e70822e3/attachment.html>


More information about the Uh-utility mailing list