[util] WHA electrical upgrades.

Thomas Slater SLATERT at upstate.edu
Fri Sep 11 14:53:45 EDT 2026


UPSTATE PHYSICAL PLANT
NOTIFICATION
Notification Type:
Planned Outage
☐Other: __________________________
Utility / Service Affected:
Electrical
☐Other: __________________________
Subject:
To support the WHA electrical upgrades]
To support: Contractor is changing feeder wires to building normal lighting panels.
Date:
9/16/2026
Time(s):
0630 to 0830 for 9th floor Kitchen, 0630 to 1430 for floor’s 6,7,8
Location:
WHA
Affected Areas / Equipment
(Room, Equipment ID, etc.):
The 9th floor kitchen will see a loss of normal power to select kitchen equipment for 2 hrs.  This is being coordinated with the staff.
Floors 6,7,8 will see a loss of normal power to the building lighting for 8 hours
This will allow contractor access to replace raceways.
Impact (What will be interrupted
and what will remain operational):
There will be no loss of normal power (outlets).  There will be emergency lighting.
There will be no loss of Emergency Power
Note:
Please check your equipment as a precaution.
Questions or Concerns
If you have any questions or concerns, please contact:
Name:
John Ders
Name:

Department:
Design & Construction
Department:

Phone:
315-243-5974
Phone:

Email:
dersj at upstate.edu
Email:

Thank you for your cooperation and understanding while this work is being completed.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/wh-set-utility/attachments/20260911/bd41a8ff/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: WHA 091626 floors 6 through 9.docx
Type: application/vnd.openxmlformats-officedocument.wordprocessingml.document
Size: 39434 bytes
Desc: WHA 091626 floors 6 through 9.docx
URL: <http://lists.upstate.edu/pipermail/wh-set-utility/attachments/20260911/bd41a8ff/attachment.docx>


More information about the Wh-set-utility mailing list