[util] WHA electrical upgrade

Anne Hodges HodgesA at upstate.edu
Thu Mar 12 13:30:56 EDT 2026


The WHA electrical upgrade project requires a shutdown to add additional breakers on the South side of WHA (south of the 4 bank elevators).



This work is being scheduled for March 24th at 6:00 AM till 2:00 PM.



Rooms affected will be :



1273, 1273B, 1277, 1279



2273, 2273C, 2273D, 2277, 2287, 2293, 2297, 2301, 2303



3275, 3289, 3290, 3297



4279, 4285, 4288, 4290, 4291, 4292, 4297



5291, 5293, 5295



7290, 7292





This will affect any outlet labeled ELP-1S, ELP-2S, ELP-3S, ELP-4S, ELP-5S, ELP-6S, ELP-7S.  The number(1s/2s etc) is the corresponding floor and the outlet will be  RED.  If you have anything that is plugged into one of these outlets it should be transferred to a normal outlet the day before the outage.  If it isn’t a standard 110 v outlet plug, I will need to know.  Some of the freezers are 208V.



I will be going to each lab to check for irregular cords so that we can get them addressed and a place to plug into.



If you have any questions or concerns, please feel free to contact me at 315-243-5974.

John Ders.



-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.upstate.edu/pipermail/wha-utility/attachments/20260312/900597c8/attachment.html>


More information about the Wha-utility mailing list